Calculating Legal Framework Materials (Part 1)
Since we covered formwork installation last time, this time we'll look at the rebar used for formwork framing.
Legal Framework Assembly Worker
- Let's find the area.
- Determine the maximum length from the drawing.
- Check the rebar size.
- Check the overlap of the rebar.
- Check the length of each reinforcing bar.
My method is,
We will make a provisional calculation by treating the triangular mountain as a square.
For example, let’s say we have a 214 m² slope. Suppose we install a 300-frame retaining wall.
- Area: 214 m²
- Length: 18 m
- Reinforcing bar diameter: D13
- Reinforcing bar overlap: D13 × 40 = 520 mm
- Length of rebar used: 5 m

Since the maximum length is about 18 m, 214 m² ÷ 18 m = 12 m
The lateral length shall be 12 meters.
(It's okay if it differs from reality.)
Vertical Reinforcing Bars
Since the length is 18 meters,
18 m ÷ 5 m (length of rebar used) = 3 bars, with 3 m remaining
There will be three overlaps in the rebar.
5 m + 5 m + 5 m + 3 m = 18 m
Since the overlap of the rebar is 0.52 m per location,
0.52 m × 3 locations = 1.56 m
3 pieces of rebar at 5 m each + 3 m + 1.56 m = 19.56 m
Since Frame 300 uses four reinforcing bars on the top and bottom,
19.56 m × 4 = 78.24 m per beam
Horizontal Length ÷ Frame Spacing = Span
12 m ÷ 2 m = 6 spans
6 spans + 1 = 7 beams (same number of intersections)
7 beams × 78.24 m = 547.68 m
547.68 m × 0.995 kg/m (unit volume weight of D13 rebar) = 545 kg
That's how it works.
Next time, it's the side view.
*There are many ways to calculate this.
This method isn't the only one.
See you later.