Price List for Ground Anchor Drilling | Unit Prices by Soil Type

Hello, everyone.

This is Enta.

 

I was working on a quote for Anchor when something occurred to me.

Do you have a general idea of the estimated cost?

I haven't done that, but,

The market prices are listed, so you can just check the list, but ground anchors aren't included in the list, are they?

This is just a rough outline in bullet points. I'll put it together into a list sometime.

 

All of the following are packages.

Drilling (in no particular order)

Available (skid-type) Double-pipe system 90 mm Cohesive soil and sandy soil

1 m: 6,453 yen

Available (Skid-type) Double-pipe System 90 mm Soft Rock

1 m: 13,080 yen

Available (Skid-type) Double-Pipe System, 90 mm, Gravel-Mixed Soil

1 m: 16,230 yen

Available (Skid-type) Double-pipe system, 90 mm, clayey soil

1 m: 10,610 yen

Available (Skid-type) Double-pipe System 90mm Hard Rock

1 m: 17,240 yen

 

These are the amounts as of March 2017.

Just for your information.

Unit prices are rising, albeit slightly.

But! However,Work has decreased, and companies are competing to lower their unit prices.

We'll go after the work even if it means cutting back on social insurance premiums.

Is this really what the government wants??

Is this really okay??

In the end, all the construction companies will go under together, lol.

 

I'm looking forward to the civil engineering unit prices for April and July lol

 

See you later.