Hello, everyone.
This is Enta.
I've been in Yokohama and Tokyo for the past few days.
Big cities really are amazing, lol.
What do I mean? Well, there are just so many people.

It makes me wonder, “Are there really fewer people these days?”
It would be fine if there were just a few people walking, so,
I can't help but think, "I wish you'd become a slope engineer or an anchor specialist," lol.
But that's beside the point.
Displays the anchor worker's setup process in a tree view.
Order Received
( (purchased the book)
↓
(Anchor Body · Cement)
↓
On-site inspection, verification of drilling locations (verification of hole numbers)
(Drawing Data and On-Site Verification)
↓
Confirming the Scaffolding Assembly Location
(The vertical height from the pouring position, measured at the drilling angle, marks the start of the scaffolding.)
(Ideal Ground Level for Anchor Drilling)
↓
Based on our estimate of when the scaffolding will be completed,
Arrangements for Delivering the Drilling Rig and Crane Operations
↓
Scaffolding Completed
(Extension of the top-most scaffold level; as-built cross-sections on the left and right; measurements and photographs for each level)
↓
Anchor Crew Onboard
↓
Measuring Anchor Bodies and Supervising Receiving
(Free length, fixed length, excess tension length)
↓
Start Drilling
(Check the angle and drilling depth on the drawing)
(Digital Slant, Measuring Rod, Slime Case)
↓
Supervision of Cement Slurry Mixing
(Test specimen, flow value, NEXCO: temperature,
(Mud Balance, Breeding, Salt Content)
(Flow cones, etc.)
↓
Photos of the drilling, insertion, injection, and pressurization processes are
Decide in advance how often you will take photos.
(It’s safest to take photos of everything, but taking a photo of the situation about once every 10 shots is fine.)
↓
Inspection of the finished work, including drilling length, drilling angle, and drilling diameter
(Estimating the completion date based on the number of meters drilled per day)
↓
Book a jack rental for around the expected date.
↓
The as-built dimensions of each level of the scaffolding are measured and photographed every time a level is completed.
↓
We dismantled the scaffolding and set up temporary scaffolding.
↓
Prepare and submit a test plan for stress stabilization
(Created during drilling)
↓
Confirmation Exams (All except Aptitude Tests)
(Review the design calculations, design drawings, etc.)
(Set up measuring instruments such as calipers)
FSC Fujiwara Industries, Inc.etc.
↓
Observation of Qualification and Verification Tests
↓
Dismantling of Tension Scaffolding
(Arrangements for removing the drilling machine, arranging for a truck)
↓
Head Retouching (A few areas in the photo are sufficient)
(Baby Thunder, rebar-cutting blades, cutters, scrapers, etc.)
↓
Site Cleanup
↓
Wrap-up
*For compressive strength tests, unless conducted at a public testing facility, a representative or a government official must be present.
*Even with fast-setting cement, if the bond has not set by the third day, the three-day strength is not required.
(Either 7-day intensity or 28-day intensity)
When one of our younger employees is feeling lost, they need to know exactly where they stand right now.
To double-checkCheat Sheet?

If you can see what lies ahead, you'll make fewer mistakes, and
You might be able to double-check and notice any discrepancies.
Well, that's it for now.



