The wrapping work on the catch basin we were constructing last month is now complete.
I'm glad it ended so nicely and smoothly.
As for the catch basin work, since we simply cannot manufacture the louver plates in-house, another company will handle that part.
It would be nice if we could handle this part too, but we can’t exactly go out and buy a machine just for that, so we’ll have to outsource it, right?
Specialized construction work around here has been insanely expensive lately, so even the general contractors aren't making any money.
Specialized construction work really does cost a lot, doesn't it?
That said, our drilling work is actually a pretty specialized kind of job, too~
The unit price isn't that... lol
Is it actually more common than it looks?

The design was originally for the VP40, but we went ahead and included the VP75 well-maintenance pipe as a courtesy!
This is often overlooked in the design, but if a drainage pipe isn't installed, water will seep down between the natural ground and the liner plate, and
The natural ground is deteriorating.
A well casing is essential to ensure that water flows properly into the well, isn't it?
Is this the kind of thing you'd expect from a design consultant?
Well, at least it's over, so I'll call it a win lol