Slope Stabilization Problem 2That's it.
Ground An—Engineering Edition
There are 30 ground anchors arranged in 10 rows horizontally and 3 columns vertically.
This is a reverse-wrap installation for each section.
*"Reverse-excavation construction" refers to a method in which the first layer is excavated, ground anchors are installed, and then the second layer is excavated.
Conditions
Earthwork excavation takes three days per stage.
Two drill holes per day
Tension: 2 days per step
The machine is a crawler-type rotary percussion machine
Construction downtime is one day per section (preparatory work)
The pressure plates are made of lightweight steel; five sets are installed per day (with no unevenness and no backing plates).

What is the shortest possible construction period?
Please consider how to carry out the work and what method would allow it to be completed as quickly as possible.
If you're leaving a comment, please use bullet points, as your response will be in paragraph form.