The "Design and Construction Standards for Ground Anchors" and the accompanying commentary state that
Pull-out Test P182
| Cycle | Test Load | Load Holding Time (min) | |
|---|---|---|---|
| Sandy soil-rock formation | Cohesive Soil | ||
| 1 | 0.40 Tp | 15 | 15 |
| 2 | 0.55 Tp | 15 | 15 |
| 3 | 0.70 Tp | 30 | 60 |
| 4 | 0.80 Tp | 30 | 60 |
| 5 | 0.90 Tp | 30 | 60 |
| 6 | 1.00 Tp | 60 | 180 |
Aptitude Test, p. 189
| Cycle | Test Load | Load Holding Time (min) | ||||
|---|---|---|---|---|---|---|
| Rank B | Rank A | Rank B | Rank A | |||
| Sandy soil-rock formation | Cohesive Soil | Sandy soil-rock formation | Cohesive Soil | |||
| 1 | 0.40 Td | 0.40 Td | 1 | 1 | 15 | 15 |
| 2 | 0.60 Td | 0.60 Td | 1 | 1 | 15 | 15 |
| 3 | 0.80 Td | 0.80 Td | 5 | 5 | 30 | 60 |
| 4 | 1.00 Td | 1.00 Td | 5 | 5 | 30 | 60 |
| 5 | 1.10Td | 1.25Td | 30 | 60 | 60 | 180 |
It says so.
However,You can shorten both of them.
It says...
Based on my roughly 20 years of experience, for loads in the 1,000 kN class,
It takes about 30 minutes for the creep to stabilize,It takes about 15 minutes at the earliest.
The smaller the load, the shorter the time.
It's fine to maintain the holding load as planned, but,A waste of timeThat's it.